Skip to Content

UPDATE: Discovery of unmarked, underground utility lines should not delay 8th Street project in Colorado Springs

COLORADO SPRINGS, Colo. (KRDO) — Two recent construction projects showed how the discovery of underground, unmarked utility lines delayed progress for several months.

However, Colorado Springs Utilities (CSU) said that a similar discovery on the ongoing 8th Street improvements project should not delay work there.

In a release issued last week, city officials revealed that after crews recently finished drilling to locate utility lines under the street, they "discovered many previously unmarked underground utilities between Motor City Drive and the Fountain Creek bridge."

With a water main replacement as part of the project, crews must ensure they can account for every utility line — who it belongs to, whether it is active or inactive, and what to do with it.

On Wednesday, CSU spokesperson Cassie Melvin explained that some of the unmarked lines were installed before modern record-keeping, which is not unusual.

"The newly-identified lines are now being recorded and incorporated into updated design plans," she said. "Some revisions are being made. However, the overall project is not changing."

The utility line situation could be why the water main replacement, originally scheduled to begin this winter, hasn't begun yet; the start date is now planned for sometime this spring.

A similar utility line issue delayed construction of the new Voyager Parkway bridge as part of the extension of Powers Boulevard north to Interstate 25, and slowed progress on relocating utility lines for the new Coral Bluffs substation on Austin Bluffs Parkway.

Overnight on Wednesday, as scheduled, crews closed the west side of the Fountain Creek bridge on 8th Street — kicking off a monthlong phase to complete repair work and rebuild the sidewalk.

The traffic pattern has changed in the area, and all lanes will be in their final configuration at the end of that phase.

On Wednesday, a milling crew arrived to begin scraping old asphalt from the bridge, allowing repairs to continue.

Officials expect the $12 million project — covering two-thirds of a mile between Cimarron Street and Motor City Drive — to end this fall, after that stretch is repaved.

Article Topic Follows: Top Stories

Jump to comments ↓

Scott Harrison

Scott is a reporter for KRDO. Learn more about Scott here.

BE PART OF THE CONVERSATION

KRDO NewsChannel 13 is committed to providing a forum for civil and constructive conversation.

Please keep your comments respectful and relevant. You can review our Community Guidelines by clicking here

If you would like to share a story idea, please submit it here.